Booking $80K months. Still short at the end of every one.
-
1What happened
The owner had been running a fencing and concrete business for four years. Revenue was up. His bank account said otherwise.
He thought he had a sales problem. He had a cash flow problem, and no way to see which jobs were causing it.
-
2Why it happened
- Two of three divisions were running below 35% gross margin
- Accounts receivable lagged cash outflows by 22 days, draining working capital every month
- Every job looked the same on the P&L, so the losing lines hid inside the winning ones
-
3What to do next
- Built a job-level P&L tracking material and labor cost per division
- Repriced the two service lines running below the floor
- Mapped receivable timing against cash outflows so the 22-day lag showed up in the forecast, not the bank balance
- Created a 12-month rolling forecast with weekly cash projections
Illustrative example. Figures are representative of the work, not a specific client.